Here is the latest road restrictions along the Regina Bypass Route.

 

Highway 1 East

Sign installation

Work adjacent to the road

Minor delays due to speed reduction

Work completed by December 20, weather permitting

(TCRF-907 and 766)

 

Pilot Butte Bridge

Work adjacent to the road

Minor delays due to speed reduction

Work completed by December 20, weather permitting

(TCRF-822)

 

Highway 33

Light pole installation

Work adjacent to the road

Shoulder closures

Minor delays due to speed reduction

Work completed by December 20, weather permitting

(TCRF-889)

 

North Service Road

Tower Road to Hwy 48

Work adjacent to the road

Single alternating traffic in sections

Minor delays due to speed reduction

Work completed by December 20, weather permitting

(TCRF-441)

 

Pearl Street

Road work and paving

Minor delays due to speed reduction

Work completed by December 20, weather permitting

(TCRF-493)

 

Pinkie Road south of Hwy 1

24-hour equipment crossing

Minor delays due to speed reduction

On going

(TCRF-540)

 

Range Road 164 near Hwy 6

24-hour equipment crossing

Minor delays due to speed reduction

On going

(TCRF-709)