Pinkie Road Road Work To Begin This Week

Pinkie Road Road Work To Begin This Week

MAPS OF NEW TRAFFIC MOVEMENTS

Pinkie Road to Rotary

Highway 1 West Update

 

DURING the upcoming weeks our construction teams will be working on the West portion of the Bypass.

In order to complete the work, we will be shifting traffic. During this phase of the work, which will last until the end of August, you can expect the following traffic realignments, which are scheduled to begin as soon as Friday, July 20, weather permitting.

 

East Bound Traffic on Highway 1 to GTH and Dewdney Avenue
All westbound Highway 1 motorists taking the off ramp to the GTH will now travel on the new West Regina ByPass (formerly Pinkie Road).

 

West Bound Traffic on Highway 1 to GTH and Dewdney Avenue
Eastbound Highway 1 to north bound traffic exiting to GTH will see a slight realignment on the south side of Hwy 1 that takes them over the new bridge and ramp and on to the new West Regina ByPass (formerly Pinkie Road).

 

North Bound Traffic to GTH and Dewdney Avenue
The new alignment north of Hwy 1 will move both north bound and south bound traffic on to the new West Regina ByPass (formerly Pinkie Road) that connects to Rotary Avenue then to the GTH and Dewdney Ave.

 

South Bound Traffic to Highway 1
Access from Dewdney Avenue to Highway 1 will now be via GTH, Rotary Avenue and the new West Regina Bypass (formerly Pinkie Road).

 

NOTE: During this construction phase:

Pinkie Road will be closed south of the railway tracks.

Dewdney Avenue will remain open